PGBT Widening

 
President George Bush Turnpike Widening Project Description

The PGBT Widening Project will include widening of the PGBT from Interstate 20 to State Highway 183 and from north of Belt Line Road (Irving) to SH 78 to four lanes in each direction. All widening will take place within the center median.

The project will be built in phases, and construction is underway in some sections.

  • PGBT between U.S. 75 and the Dallas North Tollway and westbound between Renner Road and U.S. 75: Construction began in May 2015 and the fourth lane opened to traffic in November 2016.
  • SH 78 to U.S. 75: Construction began in June 2017 and the fourth lane opened to traffic in October 2018
  • DNT to I-35E: Construction began in July 2017; anticipated completion: weather permitting: late 2019
  • I-35E to north of Belt Line Road (Irving): Currently in design phase
  • SH 183 to I-20: Currently in design phase
 
See Progress Report below for the latest updates.

Keeping You Informed is Important to Us

Community Meetings
Keeping the public informed about the PGBT Widening Project is a top priority for NTTA during construction. Informational meetings for members of the public will be scheduled and announced, as needed.

Invite us to your next event!
The NTTA team can meet with your civic club, homeowners association, tenants or company staff members. We can offer a brief presentation, answer your questions and provide handouts that you may share with others. Contact us at SpeakersBureau@NTTA.org.

 

Business Information Group (B.I.G.) Meetings

NTTA’s Business Information Group (B.I.G.) meetings are designed to keep business owners and managers current with progress on the PGBT Widening Project. NTTA personnel and consultants, and sometimes representatives from our partners, provide brief presentations about the projects during the sessions. 

A date for the next B.I.G. meeting has not been set. NTTA personnel will issue notices here and they will also be sent electronically to B.I.G. members prior to the meetings.

For details, please contact us at ProgressNTTA@NTTA.org or call 972-628-3134

Status
See our quarterly Corridor Progress Report for the latest information.  Fall 2018

 

 Progress in Pictures

Camera icon.pngPhoto Slideshow - View photos of the PGBT Widening Project construction.
 

 

Visuals
Take a virtual ride on the PGBT and see what it will look like when a fourth lane is added. Click image below.


 

Frequently Asked Questions
Click here for “Frequently Asked Questions” about the PGBT Widening Project.